Bencardino Excavating, Inc. will begin the paving project on Wednesday, October 2nd – weather permitting.  Temporary street signs will be posted soon.   This project should be completed by November 1st.  Below is the Street List and Paving Date list:

  1. Summit Avenue – Neshaminy Avenue to Riverview Lane – Milling Date: 10/2/19 – 10/3/19 – Paving Date: 10/15/19
  2. Marshall Avenue – Bristol Road to Wood Road – Milling Date: 10/2/19 – 10/3/19 – Paving Date: 10/15/19
  3. Libby Lane – Brownsville Road to Arrowhead Road – Milling Date: 10/2/19 – 10/3/19 – Paving Date: 10/15/19
  4. Shady Brook Lane – Bristol road to Dead End – Milling Date: 10/4/19 – 10/9/19 – Paving Date: 10/16/19
  5. Delwhit Drive – Bristol Road to Shady Brook Lane – Milling Date: 10/4/19 – 10/9/19 – Paving Date: 10/16/19
  6. Russet Lane – Crestwood Avenue to Lockwood Avenue – Milling Date: 10/4/19 – 10/9/19 – Paving Date: 10/16/19
  7. Rosewood Avenue – Meadowbrook Road to Poplar Road – Milling Date: 10/9/19 – 10/10/19 – Paving Date: 10/17/19
  8. Oak Road – Elmwood Avenue to Walnut Avenue- Milling Date: 10/9/19 – 10/10/19 – Paving Date: 10/17/19
  9. Hickory Avenue – Poplar Road to South Lake Road – Milling Date: 10/9/19 – 10/10/19 – Paving Date: 10/17/19
  10. Ann Drive – Street Road to Bruce Road – Milling Date: 10/11/19 – 10/14/19 – Paving Date: 10/18/19
  11. Bruce Road – Sterner Mill Road to David Drive – Milling Date: 10/11/19 – 10/14/19 – Paving Date: 10/18/19
  12. David Drive – Bruce Road to Jerome Road – Milling Date: 10/11/19 – 10/14/19 – Paving Date: 10/18/19
  13. 5th Street – Welcome Lane to Bustleton Pike – Milling Date: 10/11/19 – 10/14/19 – Paving Date: 10/18/19

Striping will be scheduled once all the paving is complete.

 

Please note that if weather impacts paving during a weekday, then Bencardino may work on the weekend.