Tentative Road Paving Schedule
The 2023 Road Paving Program begins Monday, September 11th. Below is the tentative schedule and is subject to change. Any changes will be updated daily.
Monday, 9/11 - Clover Lane & Richland Road will be milled.
Tuesday, 9/12 - Hoover Avenue & Rose Street will be milled.
Wednesday, 9/13 & Thursday, 9/14 - Poplar Road, E. Myrtle Avenue & Andrews Road will be milled.
Thursday, 9/14 & Friday, 9/15 - Clover Lane & Richland Road will be paved.
Friday, 9/15 - Herrick Avenue will be milled.
Monday, 9/18 & Tuesday, 9/19 - Hoover Avenue & Rose Street will be paved.
Monday, 9/18 - Penn Street & Fay Drive will be milled.
Tuesday, 9/19 & Wednesday, 9/20 - Dolton Road, Vista Street & Does Lane will be milled.
Wednesday, 9/20 & Thursday, 9/21 - Poplar Road, E. Myrtle Avenue & Andrews Road will be paved.
Friday, 9/22 - Herrick Avenue will be paved.
Monday, 9/25 - Penn Street & Fay Drive will be paved.
Tuesday, 9/26 & Wednesday, 9/27 - Dolton Road, Vista Street & Does Lane will be paved.