Roadway Maintenance & Improvement Program- Updated 9/25/25
Roadway Maintenance Program
In August, the Board of Supervisors awarded the Roadway Maintenance Program to Asphalt Maintenance Solutions, LLC (AMS). The following 6 roads will be oiled and chipped then fog sealed:
- Herrick Avenue (Crestwood to Bristol)
- Pheasant Run (Sandpiper to dead end)
- Overlook Road (Elmwood to Spring Meadow)
- Over Road (Spring Meadow to cul-de-sac)
- Cynthia Lane (Overlook to cul-de-sac)
- Somers Avenue (Over to cul-de-sac)
James D. Morrissey, Inc. has completed the prep work. AMS will be following the below schedule (weather dependent):
TUESDAY, 9/23 – apply the crack seal
WEDNESDAY, 9/24 – apply the chip seal
WEDNESDAY, 10/1 & THURSDAY, 10/2 – apply the Type II Slurry
Please note, that this process will leave loose stone chips on the roadway. After 48 hours, AMS will determine when their sweeper will remove the remaining stone chips. The final fog seal coating will be applied approximately 21 days later after the oil and chip has cured. It is important that the stone chips are left loose for a specific amount of time to allow vehicle traffic to compact them into the asphalt emulsion. This process helps cure the new surface, ensuring a strong, long-lasting pavement seal.