2026 Road Paving Program is Underway
🚧 2026 ROAD PAVING PROGRAM IS UNDERWAY!
Lower Southampton Township’s 2026 Road Paving Program began today, Monday, November 2nd!
Below is the tentative schedule for milling and paving operations:
MILLING SCHEDULE
- Monday, November 2: Hilton, Crescent, Summit, Woodside & Arrowhead
- Tuesday, November 3: 2nd, N. Center & Hazel
- Wednesday, November 4:Â 5th, Skyline & Village
- Thursday, November 5: Hilltop & Steamridge
PAVING SCHEDULE
- Monday, November 9: Hilton, Crescent, Summit, Woodside & Arrowhead
- Tuesday, November 10: 2nd, N. Center & Hazel
- Wednesday, November 11: 5th, Skyline & Village
- Thursday, November 12: Hilltop & Steamridge
Please Note: This is a tentative schedule and is subject to change due to weather and other unforeseen circumstances. Residents should anticipate possible traffic delays and use caution when traveling through active work zones.
Thank you for your patience and cooperation as we make improvements to our Township roadways!