Tentative Road Paving Schedule
The 2023 Road Paving Program begins Monday, September 11th. Below is the tentative schedule and is subject to change. Any changes will be updated daily.
Monday, 9/11 – Clover Lane & Richland Road will be milled.
Tuesday, 9/12 – Hoover Avenue & Rose Street will be milled.
Wednesday, 9/13 & Thursday, 9/14 – Poplar Road, E. Myrtle Avenue & Andrews Road will be milled.
Thursday, 9/14 & Friday, 9/15 – Clover Lane & Richland Road will be paved.
Friday, 9/15 – Herrick Avenue will be milled.
Monday, 9/18 & Tuesday, 9/19 – Hoover Avenue & Rose Street will be paved.
Monday, 9/18 – Penn Street & Fay Drive will be milled.
Tuesday, 9/19 & Wednesday, 9/20 – Dolton Road, Vista Street & Does Lane will be milled.
Wednesday, 9/20 & Thursday, 9/21 – Poplar Road, E. Myrtle Avenue & Andrews Road will be paved.
Friday, 9/22 – Herrick Avenue will be paved.
Monday, 9/25 – Penn Street & Fay Drive will be paved.
Tuesday, 9/26 & Wednesday, 9/27 – Dolton Road, Vista Street & Does Lane will be paved.