Tentative Road Paving Schedule
Tentative Road Paving Schedule
The 2023 Road Paving Program begins Monday, September 11th. Below is the tentative schedule and is subject to change. Any changes will be updated daily.
Monday, 9/11 – Clover Lane & Richland Road will be milled.
Tuesday, 9/12 – Hoover Avenue & Rose Street will be milled.
Wednesday, 9/13 & Thursday, 9/14 – Poplar Road, E. Myrtle Avenue & Andrews Road will be milled.
Thursday, 9/14 & Friday, 9/15 – Clover Lane & Richland Road will be paved.
Friday, 9/15 – Herrick Avenue will be milled.
Monday, 9/18 & Tuesday, 9/19 – Hoover Avenue & Rose Street will be paved.
Monday, 9/18 – Penn Street & Fay Drive will be milled.
Tuesday, 9/19 & Wednesday, 9/20 – Dolton Road, Vista Street & Does Lane will be milled.
Wednesday, 9/20 & Thursday, 9/21 – Poplar Road, E. Myrtle Avenue & Andrews Road will be paved.
Friday, 9/22 – Herrick Avenue will be paved.
Monday, 9/25 – Penn Street & Fay Drive will be paved.
Tuesday, 9/26 & Wednesday, 9/27 – Dolton Road, Vista Street & Does Lane will be paved.